The purpose of a Conditional Use Permit is to insure that the use requested will be compatible with other existing and permitted uses located in the area.
The procedure for the processing of a Conditional Use Permit application is as follows:
1. Submit complete application to the Community Development Department on the Thursday six weeks before the scheduled PEC meeting.
2. Secretary will set the date of public hearing before the Commission at a regular meeting and will circulate the required hearing notices.
3. The Commission either approves, approves with conditions, or denies applicant's application.
4. The Commission's decision is final and is subject to appeal to the City Council within twenty (20) calendar days.
The Community Development Department staff will be happy to assist you. Should you have any questions concerning your application, please do not hesitate to contact the department at (562) 866-9771, ext. 2343.
Download a Conditional Use Permit form.
( View PDF )